Assessment Year | 1996 |
---|---|
Principal Product | carboard containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 111 |
Plant Area |
160,000
ft2
|
Annual Production | 442,000
thousand feet
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $118,506 | 2,392,438 |
kWh
|
$0.050 |
Electricity Demand | $20,290 | 7,386 |
kW-mo/yr
|
$2.75 |
Electricity Fees | $35,931 | - |
|
- |
Natural Gas | $62,261 | 24,979 |
MMBtu
|
$2.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,914 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,192 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,291 | $891 |
$925
19,343
kWh
|
$140
-
kW-mo/yr
|
$226 | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $180 | $644 |
$111
2,345
kWh
|
$34
-
kW-mo/yr
|
$35 | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,901 | $1,000 | - | - | - |
$2,901
-
MMBtu
|
- | |
04 | 3.4113: Treat and reuse rinse waters | $8,542 | $36,987 |
$(-71.0)
(-1,465)
kWh
|
$(-5.0)
-
kW-mo/yr
|
- | - |
$8,618
-
Tgal
|
|
TOTAL RECOMMENDED | $12,914 | $39,522 |
$965
20,223
kWh
|
$169
-
kW-mo/yr
|
$261 |
$2,901
-
MMBtu
|
$8,618
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,192 | $1,891 |
$925
19,343
kWh
|
$140
-
kW-mo/yr
|
$226 |
$2,901
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs