| Assessment Year | 1995 |
|---|---|
| Principal Product | air bags |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 217 |
| Plant Area |
100,000
ft2
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $138,439 | 2,894,783 |
kWh
|
$0.048 |
| Natural Gas | $6,967 | 1,708 |
MMBtu
|
$4.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,687 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,413 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,709 | $3,855 |
$3,709
50,703
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $579 | $1,200 | - |
$579
-
MMBtu
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $5,047 | $200 |
$5,047
68,875
kWh
|
- | - | |
| 04 | 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency | $1,870 | $5,100 |
$1,870
25,791
kWh
|
- | - | |
| 05 | 3.7196: Use re-usable filters | $1,400 | $420 | - | - |
$1,400
-
lb
|
|
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $957 | $800 |
$1,082
6,741
kWh
|
$(-125.0)
-
MMBtu
|
- | |
| 07 | 2.6214: Shut off pilots in standby equipment | $125 | $20 | - |
$125
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $13,687 | $11,595 |
$11,708
152,110
kWh
|
$579
-
MMBtu
|
$1,400
-
lb
|
||
| TOTAL IMPLEMENTED | $4,413 | $5,075 |
$3,709
50,703
kWh
|
$704
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs