ITAC Assessment: MO0267
ITAC logo
ITAC Assessment: MO0267
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Hardwood Oak Flooring
NAICS
n/a
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 180,972
ft2
Annual Production 12,000,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,183 1,414,713
kWh
Electricity Demand $42,066 998
kW-mo/yr
Electricity Fees $4,693 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,119

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $1,983 $4,472 $1,347
30,774
kWh
$636
-
kW-mo/yr
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $436 - $297
6,741
kWh
$139
-
kW-mo/yr
- - -
03 3.5313: Increase amount of waste recovered for resale $2,700 - - - $2,700
-
lb
- -
04 2.1113: Reduce combustion air flow to optimum - - - - - - -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $24,480 - - - - - $24,480
06 4.423: Move product using mechanical means $38,556 $5,053 - - - $38,556 -
TOTAL RECOMMENDED $68,155 $9,525 $1,644
37,515
kWh
$775
-
kW-mo/yr
$2,700
-
lb
$38,556 $24,480
TOTAL IMPLEMENTED $5,119 $4,472 $1,644
37,515
kWh
$775
-
kW-mo/yr
$2,700
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs