ITAC Assessment: MO0265
ITAC logo
ITAC Assessment: MO0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Plastic Pipe, Electric Conduit
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 64,000
ft2
Annual Production 100,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $771,922 19,546,601
kWh
Electricity Demand $232,434 2,904
kW-mo/yr
Electricity Fees $62,569 -
Natural Gas $32,010 4,752
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $173,201 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $118,116

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $316 $379 $156
3,810
kWh
$160
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $25,036 $24,912 $20,338
513,482
kWh
$4,698
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,525 $200 $2,053
51,876
kWh
$472
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,218 - $5,049
127,491
kWh
$1,169
-
kW-mo/yr
- -
05 3.5316: Contract a wood pallet recycling company $24,000 - - - $24,000
-
lb
-
06 4.441: Install automatic packing equipment $62,546 $14,500 - - - $62,546
07 4.444: Install system to collect scrap $52,560 $14,000 - - - $52,560
TOTAL RECOMMENDED $173,201 $53,991 $27,596
696,659
kWh
$6,499
-
kW-mo/yr
$24,000
-
lb
$115,106
TOTAL IMPLEMENTED $118,116 $39,791 $25,543
644,783
kWh
$6,027
-
kW-mo/yr
$24,000
-
lb
$62,546
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs