| Assessment Year | 1999 |
|---|---|
| Principal Product | Plastic Pipe, Electric Conduit |
| NAICS |
n/a
|
| SIC | 3084: Plastics Pipe |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
64,000
ft2
|
| Annual Production | 100,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $771,922 | 19,546,601 |
kWh
|
$0.039 |
| Electricity Demand | $232,434 | 2,904 |
kW-mo/yr
|
$80.04 |
| Electricity Fees | $62,569 | - |
|
- |
| Natural Gas | $32,010 | 4,752 |
MMBtu
|
$6.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $173,201 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $118,116 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $316 | $379 |
$156
3,810
kWh
|
$160
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $25,036 | $24,912 |
$20,338
513,482
kWh
|
$4,698
-
kW-mo/yr
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,525 | $200 |
$2,053
51,876
kWh
|
$472
-
kW-mo/yr
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,218 | - |
$5,049
127,491
kWh
|
$1,169
-
kW-mo/yr
|
- | - | |
| 05 | 3.5316: Contract a wood pallet recycling company | $24,000 | - | - | - |
$24,000
-
lb
|
- | |
| 06 | 4.441: Install automatic packing equipment | $62,546 | $14,500 | - | - | - | $62,546 | |
| 07 | 4.444: Install system to collect scrap | $52,560 | $14,000 | - | - | - | $52,560 | |
| TOTAL RECOMMENDED | $173,201 | $53,991 |
$27,596
696,659
kWh
|
$6,499
-
kW-mo/yr
|
$24,000
-
lb
|
$115,106 | ||
| TOTAL IMPLEMENTED | $118,116 | $39,791 |
$25,543
644,783
kWh
|
$6,027
-
kW-mo/yr
|
$24,000
-
lb
|
$62,546 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs