| Assessment Year | 1999 |
|---|---|
| Principal Product | Iron Oxide Pigments |
| NAICS |
n/a
|
| SIC | 2816: Inorganic Pigments |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
210,000
ft2
|
| Annual Production | 38,000,000
lb
|
| Production Hrs. Annual | 5,320
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $616,287 | 15,273,447 |
kWh
|
$0.040 |
| Electricity Demand | $43,247 | 2,141 |
kW-mo/yr
|
$20.20 |
| Electricity Fees | $67,205 | - |
|
- |
| Natural Gas | $759,510 | 368,477 |
MMBtu
|
$2.06 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $46,103 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,340 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,048 | $3,071 |
$905
20,223
kWh
|
$143
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $27,744 | $41,879 |
$25,558
570,633
kWh
|
$2,186
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,759 | - |
$3,460
77,374
kWh
|
$299
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.1175: Use a different or recycled raw material | $700 | - | - | - |
$700
-
lb
|
- | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $9,212 | - | - | - | - | - | $9,212 | |
| 06 | 4.611: Begin a practice of predictive / preventative maintenance | $3,640 | $3,700 | - | - | - | $3,640 | - | |
| TOTAL RECOMMENDED | $46,103 | $48,650 |
$29,923
668,230
kWh
|
$2,628
-
kW-mo/yr
|
$700
-
lb
|
$3,640 | $9,212 | ||
| TOTAL IMPLEMENTED | $4,340 | $3,700 | - | - |
$700
-
lb
|
$3,640 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs