ITAC Assessment: MO0261
ITAC logo
ITAC Assessment: MO0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Iron Oxide Pigments
NAICS
n/a
SIC 2816: Inorganic Pigments
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 210,000
ft2
Annual Production 38,000,000
lb
Production Hrs. Annual 5,320
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $616,287 15,273,447
kWh
Electricity Demand $43,247 2,141
kW-mo/yr
Electricity Fees $67,205 -
Natural Gas $759,510 368,477
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,103 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,340

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,048 $3,071 $905
20,223
kWh
$143
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $27,744 $41,879 $25,558
570,633
kWh
$2,186
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,759 - $3,460
77,374
kWh
$299
-
kW-mo/yr
- - -
04 3.1175: Use a different or recycled raw material $700 - - - $700
-
lb
- -
05 2.8114: Change rate schedules or other changes in utility service $9,212 - - - - - $9,212
06 4.611: Begin a practice of predictive / preventative maintenance $3,640 $3,700 - - - $3,640 -
TOTAL RECOMMENDED $46,103 $48,650 $29,923
668,230
kWh
$2,628
-
kW-mo/yr
$700
-
lb
$3,640 $9,212
TOTAL IMPLEMENTED $4,340 $3,700 - - $700
-
lb
$3,640 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs