| Assessment Year | 1997 |
|---|---|
| Principal Product | Color Separations |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 365 |
| Plant Area |
104,654
ft2
|
| Annual Production | 254,069
units
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $135,739 | 2,721,571 |
kWh
|
$0.050 |
| Electricity Demand | $12,047 | 603 |
kW-mo/yr
|
$19.98 |
| Electricity Fees | $15,284 | - |
|
- |
| Natural Gas | $6,891 | 1,205 |
MMBtu
|
$5.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,945 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,859 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.432: Cross-train personnel to avoid lost time | $12,968 | $25,000 | - | - | - | $12,968 | |
| 02 | 4.514: Re-arrange equipment layout to reduce handling costs | $5,861 | $12,500 | - | - | - | $5,861 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,219 | $9,884 |
$10,691
192,849
kWh
|
$528
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,779 | $1,126 |
$4,553
82,063
kWh
|
$226
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $617 | $1,104 |
$593
10,844
kWh
|
$24
-
kW-mo/yr
|
- | - | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,440 | $5,240 | - | - |
$4,440
-
lb
|
- | |
| 07 | 3.7196: Use re-usable filters | $1,061 | $1,515 | - | - |
$1,061
-
lb
|
- | |
| TOTAL RECOMMENDED | $40,945 | $56,369 |
$15,837
285,756
kWh
|
$778
-
kW-mo/yr
|
$5,501
-
lb
|
$18,829 | ||
| TOTAL IMPLEMENTED | $21,859 | $23,510 |
$15,244
274,912
kWh
|
$754
-
kW-mo/yr
|
- | $5,861 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs