ITAC Assessment: MO0211
ITAC logo
ITAC Assessment: MO0211
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Curtains
NAICS
n/a
SIC 2391: Curtains and Draperies
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area 50,000
ft2
Annual Production 1,300,000
pieces
Production Hrs. Annual 3,380
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,262 682,884
kWh
Electricity Fees $2,506 -
Natural Gas $14,585 1,742
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,065 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,243

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 4.711: Initiate a total quality management program $17,085 $25,000 - - $17,085
02 4.432: Cross-train personnel to avoid lost time $6,120 $15,000 - - $6,120
03 4.514: Re-arrange equipment layout to reduce handling costs $5,000 $12,500 - - $5,000
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,571 $7,904 $3,571
57,151
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,415 $2,023 $3,415
54,513
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $209 $345 $209
3,224
kWh
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $3,125 $80 $3,125
49,824
kWh
- -
08 2.4133: Use most efficient type of electric motors $708 $1,794 $708
11,430
kWh
- -
09 2.4321: Upgrade obsolete equipment $7,800 $3,040 - $7,800
-
lb
-
10 3.7196: Use re-usable filters $1,032 $1,236 - $1,032
-
lb
-
TOTAL RECOMMENDED $48,065 $68,922 $11,028
176,142
kWh
$8,832
-
lb
$28,205
TOTAL IMPLEMENTED $15,243 $31,317 $4,123
65,943
kWh
- $11,120
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs