| Assessment Year | 2018 |
|---|---|
| Principal Product | AGM/Deep Cycle Lead Acid Batteries |
| NAICS | 335911: Storage Battery Manufacturing |
| SIC | 3694: Electrical Equipment for Internal Combustion Engines |
| Sales Range | $50 M to 100M |
| # of Employees | 215 |
| Plant Area |
291,000
ft2
|
| Annual Production | 930,000
units
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,608,403 | 31,201,501 |
kWh
|
$0.084 |
| Natural Gas | $185,718 | 28,873 |
MMBtu
|
$6.43 |
| TOTAL YEARLY COSTS | $2,794,121 | |||
| RECOMMENDED SAVINGS* | $298,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $160,596 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $14,228 | $263 |
$14,228
169,380
kWh
|
- | |
| 02 | 2.7229: Air condition only space necessary | $5,518 | $200 |
$5,518
65,696
kWh
|
- | |
| 03 | 2.2211: Use optimum temperature | $29,211 | $1,600 |
$29,211
347,751
kWh
|
- | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $55,747 | $3,800 |
$55,747
663,660
kWh
|
- | |
| 05 | 2.7135: Install occupancy sensors | $41,023 | $3,991 |
$41,023
481,800
kWh
|
- | |
| 06 | 2.2511: Insulate bare equipment | $12,211 | $1,242 | - |
$12,211
-
MMBtu
|
|
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $42,215 | $10,400 |
$42,215
502,561
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48,406 | $38,834 |
$48,406
576,259
kWh
|
- | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $49,820 | $207,295 |
$49,820
593,101
kWh
|
- | |
| TOTAL RECOMMENDED | $298,380 | $267,625 |
$286,169
3,400,208
kWh
|
$12,211
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $160,596 | $53,297 |
$160,596
1,911,860
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs