ITAC Assessment: MO0200
ITAC logo
ITAC Assessment: MO0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Components for Axles, Light Trucks and Heavy Pick-UP Trucks
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 370
Plant Area 140,000
ft2
Annual Production 3,400,000
pieces
Production Hrs. Annual 7,700
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,632 4,890,387
kWh
Electricity Demand $49,134 989
kW-mo/yr
Electricity Fees $15,109 -
Natural Gas $360,229 116,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,935 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,341

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 4.432: Cross-train personnel to avoid lost time $22,150 $20,000 - - - $22,150
02 4.711: Initiate a total quality management program $17,554 $15,000 - - - $17,554
03 4.611: Begin a practice of predictive / preventative maintenance $13,440 $5,500 - - - $13,440
04 4.514: Re-arrange equipment layout to reduce handling costs $4,050 $10,000 - - - $4,050
05 2.4221: Install compressor air intakes in coolest locations $7,176 $333 $5,924
151,231
kWh
$1,252
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,809 $4,216 $1,518
38,687
kWh
$291
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $151 $345 $131
3,224
kWh
$20
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $164 $179 $139
3,517
kWh
$25
-
kW-mo/yr
- -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $991 - $817
20,809
kWh
$174
-
kW-mo/yr
- -
10 2.4133: Use most efficient type of electric motors $1,906 $4,214 $1,573
40,152
kWh
$333
-
kW-mo/yr
- -
11 3.5311: Recover and reuse waste material $9,720 - - - $9,720
-
lb
-
12 4.711: Initiate a total quality management program $1,824 $2,200 - - $1,824
-
lb
-
TOTAL RECOMMENDED $80,935 $61,987 $10,102
257,620
kWh
$2,095
-
kW-mo/yr
$11,544
-
lb
$57,194
TOTAL IMPLEMENTED $65,341 $49,787 $10,102
257,620
kWh
$2,095
-
kW-mo/yr
- $53,144
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs