| Assessment Year | 1996 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
150,000
ft2
|
| Annual Production | 7,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $362,905 | 6,445,487 |
kWh
|
$0.056 |
| Electricity Demand | $34,987 | 15,688 |
kW-mo/yr
|
$2.23 |
| Natural Gas | $347,176 | 142,476 |
MMBtu
|
$2.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,300 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,182 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,123 | $1,273 |
$1,008
17,878
kWh
|
$115
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,118 | $5,640 |
$2,792
49,531
kWh
|
$326
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $99 | - |
$94
1,758
kWh
|
$5
-
kW-mo/yr
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $827 | - |
$744
13,189
kWh
|
$83
-
kW-mo/yr
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $3,613 | $9,138 |
$3,247
57,737
kWh
|
$366
-
kW-mo/yr
|
- | |
| 06 | 3.5221: Recycle casting sand | $9,520 | $320 | - | - |
$9,520
-
lb
|
|
| TOTAL RECOMMENDED | $18,300 | $16,371 |
$7,885
140,093
kWh
|
$895
-
kW-mo/yr
|
$9,520
-
lb
|
||
| TOTAL IMPLEMENTED | $15,182 | $10,731 |
$5,093
90,562
kWh
|
$569
-
kW-mo/yr
|
$9,520
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs