| Assessment Year | 1996 |
|---|---|
| Principal Product | Reconstituted Wood Products |
| NAICS |
n/a
|
| SIC | 2493: Reconstituted Wood Products |
| Sales Range | $10 M to 50M |
| # of Employees | 165 |
| Plant Area |
70,000
ft2
|
| Annual Production | 5,700,000
lb
|
| Production Hrs. Annual | 6,100
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $38,446 | 787,515 |
kWh
|
$0.049 |
| Electricity Demand | $3,908 | 1,756 |
kW-mo/yr
|
$2.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $63,168 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,168 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $451 | $607 |
$398
7,034
kWh
|
$53
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $821 | $1,680 |
$715
12,603
kWh
|
$106
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $220 | - |
$210
3,810
kWh
|
$10
-
kW-mo/yr
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $3,279 | $5,652 |
$3,057
53,927
kWh
|
$222
-
kW-mo/yr
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $691 | - |
$643
11,430
kWh
|
$48
-
kW-mo/yr
|
- | |
| 06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $57,706 | $88,794 | - | - |
$57,706
-
lb
|
|
| TOTAL RECOMMENDED | $63,168 | $96,733 |
$5,023
88,804
kWh
|
$439
-
kW-mo/yr
|
$57,706
-
lb
|
||
| TOTAL IMPLEMENTED | $63,168 | $96,733 |
$5,023
88,804
kWh
|
$439
-
kW-mo/yr
|
$57,706
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs