ITAC Assessment: MO0145
ITAC logo
ITAC Assessment: MO0145
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product jeans
NAICS
n/a
SIC 2325: Men's and Boys' Separate Trousers and Slacks
Sales Range $10
M
to 50
M
# of Employees 340
Plant Area 39,315
ft2
Annual Production 2,820,000
pieces
Production Hrs. Annual 3,920
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,738 2,364,889
kWh
LPG $51,255 10,812
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,180 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,995

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings
01 2.8113: Purchase gas directly from a contract gas supplier $26,602 $779 - $(-24,653.0)
-
MMBtu
$51,255
-
MMBtu
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $17,794 $824 $20,492
305,100
kWh
- $(-2,698.0)
-
MMBtu
-
03 2.6121: Reduce hot water temperature to the minimum required $1,410 $40 $1,410
21,102
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,037 $7,975 $4,037
65,651
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,293 $1,629 $2,293
37,222
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $98 $165 $98
1,758
kWh
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,593 $640 $2,593
41,032
kWh
- - -
08 2.4221: Install compressor air intakes in coolest locations $2,282 $938 $2,282
37,222
kWh
- - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $607 $40 $607
9,965
kWh
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $413 - $413
6,448
kWh
- - -
11 2.4133: Use most efficient type of electric motors $1,902 $14,404 $1,902
30,188
kWh
- - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $311 $1,265 $311
4,689
kWh
- - -
13 2.2135: Repair and eliminate steam leaks $838 $100 - - $232
-
MMBtu
$606
-
Tgal
TOTAL RECOMMENDED $61,180 $28,799 $36,438
560,377
kWh
$(-24,653.0)
-
MMBtu
$48,789
-
MMBtu
$606
-
Tgal
TOTAL IMPLEMENTED $40,995 $26,181 $13,555
216,297
kWh
$(-24,653.0)
-
MMBtu
$51,487
-
MMBtu
$606
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs