ITAC Assessment: MO0130
ITAC logo
ITAC Assessment: MO0130
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product adhesives and sealants
NAICS
n/a
SIC 2891: Adhesives and Sealants
Sales Range $10
M
to 50
M
# of Employees 146
Plant Area 160,000
ft2
Annual Production 36,205
ton
Production Hrs. Annual 5,100
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,723 1,825,616
kWh
Natural Gas $55,992 14,450
MMBtu
LPG $7,997 1,133
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,716 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,864

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7231: Use radiant heater for spot heating $19,602 $52,000 - $19,602
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,955 $4,592 $1,955
28,722
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,562 $287 $1,562
22,860
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $260 $384 $260
3,810
kWh
-
05 2.4133: Use most efficient type of electric motors $1,768 $5,510 $1,768
25,791
kWh
-
06 2.4314: Use synthetic lubricant $1,250 $480 $1,250
18,171
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $332 $320 $332
4,982
kWh
-
08 2.1311: Replace electrically-operated equipment with fossil fuel equipment $987 $1,082 $1,119
16,413
kWh
$(-132.0)
-
MMBtu
TOTAL RECOMMENDED $27,716 $64,655 $8,246
120,749
kWh
$19,470
-
MMBtu
TOTAL IMPLEMENTED $6,864 $12,175 $6,996
102,578
kWh
$(-132.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs