| Assessment Year | 1993 |
|---|---|
| Principal Product | FRAC. HP MOTORS |
| NAICS |
n/a
|
| SIC | 3621: Motors and Generators |
| Sales Range | $50 M to 100M |
| # of Employees | 650 |
| Plant Area |
n/a
|
| Annual Production | 2,500,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $481,026 | 9,118,699 |
kWh
|
$0.053 |
| LPG | $11,991 | 2,249 |
MMBtu
|
$5.33 |
| Fuel Oil #1 | $18,422 | 3,292 |
MMBtu
|
$5.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,445 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,075 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $1,408 | $1,243 | - | - |
$1,408
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,000 | $13,675 |
$4,000
75,909
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $75 | $20 |
$81
1,465
kWh
|
- | - | $(-6.0) | |
| 04 | 2.4133: Use most efficient type of electric motors | $3,376 | $9,298 |
$3,376
63,892
kWh
|
- | - | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $378 | $490 |
$378
7,034
kWh
|
- | - | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $29,208 | $43,264 |
$44,576
844,959
kWh
|
$(-15,368.0)
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $38,445 | $67,990 |
$52,411
993,259
kWh
|
$(-15,368.0)
-
MMBtu
|
$1,408
-
MMBtu
|
$(-6.0) | ||
| TOTAL IMPLEMENTED | $4,075 | $13,695 |
$4,081
77,374
kWh
|
- | - | $(-6.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs