ITAC Assessment: MO0013
ITAC logo
ITAC Assessment: MO0013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product SHOES
NAICS
n/a
SIC 3149: Footwear, Except Rubber, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 350
Plant Area
n/a
Annual Production 1,000,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,434 1,473,329
kWh
LPG $2,957 564
MMBtu
Fuel Oil #2 $7,286 1,653
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,126 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,666

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
01 2.2532: Use only amount of air necessary to prevent explosion hazard $1,504 $2,900 $781
12,896
kWh
- $723
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $630 $250 $630
10,258
kWh
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $306 $200 - $306
-
MMBtu
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $460 $50 $460
7,620
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $226 $199 $226
3,810
kWh
- -
TOTAL RECOMMENDED $3,126 $3,599 $2,097
34,584
kWh
$306
-
MMBtu
$723
-
MMBtu
TOTAL IMPLEMENTED $2,666 $3,549 $1,637
26,964
kWh
$306
-
MMBtu
$723
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs