ITAC Assessment: MO0012
ITAC logo
ITAC Assessment: MO0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product SHOE COMPONENTS
NAICS
n/a
SIC 3131: Boot and Shoe Cut Stock and Findings
Sales Range $10
M
to 50
M
# of Employees 455
Plant Area
n/a
Annual Production 50,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,455 3,152,110
kWh
LPG $5,834 909
MMBtu
Fuel Oil #2 $9,865 1,767
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,973 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,635

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings
01 2.2531: Re-size charging openings or add movable cover or door $8,174 $1,220 - $8,174
-
MMBtu
02 2.4221: Install compressor air intakes in coolest locations $3,346 $1,156 $3,346
47,773
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,338 $6,000 $2,338
33,411
kWh
-
04 2.2511: Insulate bare equipment $115 $176 $115
1,758
kWh
-
TOTAL RECOMMENDED $13,973 $8,552 $5,799
82,942
kWh
$8,174
-
MMBtu
TOTAL IMPLEMENTED $11,635 $2,552 $3,461
49,531
kWh
$8,174
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs