ITAC Assessment: MI0466
ITAC logo
ITAC Assessment: MI0466
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Construction Reinforcing Mesh and Wire
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 79,266
ft2
Annual Production 9,000
ton
Production Hrs. Annual 2,000
hrs
Location (State) Puerto Rico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $188,291 831,731
kWh
Electricity Demand $56,838 6,138
kW-mo/yr
Electricity Fees $5,385 -
TOTAL YEARLY COSTS $250,514
RECOMMENDED SAVINGS* $83,467 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.8114: Change rate schedules or other changes in utility service $1,368 $100 - - $1,368
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,332 $1,020 $7,610
33,673
kWh
$2,722
-
kW-mo/yr
-
03 2.9114: Use solar heat to make electricty $58,107 $6,400 - - $58,107
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,309 $4,560 $4,071
18,013
kWh
$238
-
kW-mo/yr
-
05 2.3212: Optimize plant power factor $8,024 $18,830 - $8,024
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,327 $3,414 $1,131
5,005
kWh
$196
-
kW-mo/yr
-
TOTAL RECOMMENDED $83,467 $34,324 $12,812
56,691
kWh
$11,180
-
kW-mo/yr
$59,475
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs