Assessment Year | 2024 |
---|---|
Principal Product | Pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
75,000
ft2
|
Annual Production | 80,000,000
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $555,460 | 9,063,120 |
kWh
|
$0.061 | |
Electricity Demand | $231,315 | 15,729 |
kW-mo/yr
|
$14.71 | |
Electricity Fees | $77,739 | - |
|
- | |
Natural Gas | $175,608 | 12,531 |
MMBtu
|
$14.01 | |
Waste Disposal Costs | |||||
Water Usage | $39,789 | 5,380 |
Tgal
|
$7.40 | |
Water Disposal | $48,631 | 5,380 |
Tgal
|
$9.04 | |
TOTAL YEARLY COSTS | $1,128,542 | ||||
RECOMMENDED SAVINGS* | $661,504 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $415,397 | $930,319 |
$160,410
2,629,677
kWh
|
$254,987
-
kW-mo/yr
|
- | - | - | |
02 | 4.812: Apply for investment incentives | $187,800 | - | - | - | - | - | $187,800 | |
03 | 2.8114: Change rate schedules or other changes in utility service | $48,834 | - | - | - | $48,834 | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,323 | $2,000 |
$3,637
59,618
kWh
|
$1,686
-
kW-mo/yr
|
- | - | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $3,889 | $70 |
$1,807
29,618
kWh
|
$2,562
-
kW-mo/yr
|
- | $(-480.0) | - | |
06 | 2.7135: Install occupancy sensors | $261 | $275 |
$261
4,282
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $661,504 | $932,664 |
$166,115
2,723,195
kWh
|
$259,235
-
kW-mo/yr
|
$48,834 | $(-480.0) | $187,800 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs