| Assessment Year | 2024 |
|---|---|
| Principal Product | Cattle Head |
| NAICS | 311611: Animal (except Poultry) Slaughtering |
| SIC | 2011: Meat Packing Plants |
| Sales Range | $1 M to 5M |
| # of Employees | 20 |
| Plant Area |
17,450
ft2
|
| Annual Production | 5,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Puerto Rico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $89,128 | 361,463 |
kWh
|
$0.25 |
| Electricity Demand | $9,185 | 965 |
kW-mo/yr
|
$9.52 |
| Electricity Fees | $2,512 | - |
|
- |
| TOTAL YEARLY COSTS | $100,825 | |||
| RECOMMENDED SAVINGS* | $9,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $3,476 | $80 |
$2,425
9,859
kWh
|
$1,051
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,706 | $3,257 |
$2,296
9,334
kWh
|
$410
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,622 | $1,720 |
$1,251
5,086
kWh
|
$371
-
kW-mo/yr
|
- | |
| 04 | 2.3212: Optimize plant power factor | $1,297 | $1,752 | - |
$1,297
-
kW-mo/yr
|
- | |
| 05 | 2.8123: Pay utility bills on time | $202 | - | - | - | $202 | |
| TOTAL RECOMMENDED | $9,303 | $6,809 |
$5,972
24,279
kWh
|
$3,129
-
kW-mo/yr
|
$202 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs