| Assessment Year | 2022 |
|---|---|
| Principal Product | Aluminum Products |
| NAICS | 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing |
| SIC | 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
52,000
ft2
|
| Annual Production | 18,800
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Puerto Rico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $551,288 | 3,437,808 |
kWh
|
$0.16 |
| Electricity Demand | $165,484 | 19,689 |
kW-mo/yr
|
$8.40 |
| Electricity Fees | $16,552 | - |
|
- |
| TOTAL YEARLY COSTS | $733,324 | |||
| RECOMMENDED SAVINGS* | $80,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,694 | $1,650 |
$18,265
114,154
kWh
|
$4,429
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,526 | $2,020 |
$15,660
97,872
kWh
|
$4,866
-
kW-mo/yr
|
- | |
| 03 | 2.3191: Use demand controller or load shedder | $12,084 | $100 | - | - | $12,084 | |
| 04 | 2.8123: Pay utility bills on time | $11,152 | - | - | - | $11,152 | |
| 05 | 2.4112: Install soft-start to eliminate nuisance trips | $5,350 | $849 |
$4,308
26,924
kWh
|
$1,042
-
kW-mo/yr
|
- | |
| 06 | 2.4238: Do not use compressed air for personal cooling | $5,300 | $9,444 |
$4,266
26,663
kWh
|
$1,034
-
kW-mo/yr
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,388 | $4,059 |
$1,922
12,012
kWh
|
$466
-
kW-mo/yr
|
- | |
| 08 | 2.7134: Use photocell controls | $1,120 | $4,014 |
$1,120
6,997
kWh
|
- | - | |
| TOTAL RECOMMENDED | $80,614 | $22,136 |
$45,541
284,622
kWh
|
$11,837
-
kW-mo/yr
|
$23,236 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs