Assessment Year | 2019 |
---|---|
Principal Product | Juices and beverages |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
Sales Range | $50 M to 100M |
# of Employees | 160 |
Plant Area |
220,000
ft2
|
Annual Production | 4,250,000,000
units
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,190,476 | 6,691,875 |
kWh
|
$0.18 | |
Electricity Demand | $187,429 | 21,984 |
kW-mo/yr
|
$8.53 | |
Electricity Fees | $10,800 | - |
|
- | |
Fuel Oil #2 | $297,068 | 15,428 |
MMBtu
|
$19.26 | |
Waste Disposal Costs | |||||
Water Usage | $339,185 | 35,000 |
Tgal
|
$9.69 | |
TOTAL YEARLY COSTS | $2,024,958 | ||||
RECOMMENDED SAVINGS* | $189,872 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $81,676 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4159: Replace treated water with well / surface water | $68,283 | $118,050 | - | - | - | - |
$68,283
-
Tgal
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,750 | $42,002 |
$26,235
147,386
kWh
|
$2,515
-
kW-mo/yr
|
- | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,615 | $19,558 |
$19,417
109,082
kWh
|
$6,198
-
kW-mo/yr
|
- | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $17,171 | $24,418 | - | - | - |
$17,171
-
MMBtu
|
- | |
05 | 2.1241: Reduce excessive boiler blowdown | $10,928 | $8,500 | - | - | - |
$9,279
-
MMBtu
|
$1,649
-
Tgal
|
|
06 | 2.7221: Lower temperature during the winter season and vice-versa | $8,814 | $480 |
$8,047
45,208
kWh
|
$767
-
kW-mo/yr
|
- | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,181 | $2,320 | - | - | - |
$8,181
-
MMBtu
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,569 | $2,020 |
$6,904
38,788
kWh
|
$665
-
kW-mo/yr
|
- | - | - | |
09 | 2.9112: Use solar heat to heat water | $7,502 | $13,650 | - | - | - |
$7,502
-
MMBtu
|
- | |
10 | 2.3212: Optimize plant power factor | $7,059 | $11,855 | - | - | $7,059 | - | - | |
TOTAL RECOMMENDED | $189,872 | $242,853 |
$60,603
340,464
kWh
|
$10,145
-
kW-mo/yr
|
$7,059 |
$42,133
-
MMBtu
|
$69,932
-
Tgal
|
||
TOTAL IMPLEMENTED | $81,676 | $72,560 |
$60,603
340,464
kWh
|
$10,145
-
kW-mo/yr
|
- |
$9,279
-
MMBtu
|
$1,649
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs