ITAC Assessment: MI0308
ITAC logo
ITAC Assessment: MI0308
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Synthetic Foam
NAICS 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $10
M
to 50
M
# of Employees 101
Plant Area 219,200
ft2
Annual Production 190,000
thousand feet
Production Hrs. Annual 4,420
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,720 1,937,597
kWh
Electricity Demand $57,588 5,557
kW-mo/yr
Electricity Fees $26,662 -
Fuel Oil #1 $19,777 1,170
MMBtu
Waste Disposal Costs
Water Usage $2,089 29,172
Tgal
TOTAL YEARLY COSTS $198,836
RECOMMENDED SAVINGS* $90,730 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,010

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #1 Savings Administrative Changes Savings
01 2.2628: Utilize a less expensive cooling method $39,159 $40,000 $24,182
503,787
kWh
$14,177
-
kW-mo/yr
- $800
02 2.7221: Lower temperature during the winter season and vice-versa $12,616 $120 $6,895
143,650
kWh
$5,720
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $11,418 $29,149 $7,066
147,198
kWh
$4,352
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,061 $1,660 $6,455
134,490
kWh
$3,606
-
kW-mo/yr
- -
05 2.7224: Reduce space conditioning during non-working hours $7,726 $120 $7,726
160,961
kWh
- - -
06 2.8226: Increase efficiency of trucks $5,724 $5,590 - - $1,974
-
MMBtu
$3,750
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,766 $3,948 $2,766
57,633
kWh
- - -
08 2.8112: Combine utility meters $720 $700 - - - $720
09 2.7135: Install occupancy sensors $540 $885 $540
11,260
kWh
- - -
TOTAL RECOMMENDED $90,730 $82,172 $55,631
1,158,979
kWh
$27,855
-
kW-mo/yr
$1,974
-
MMBtu
$5,270
TOTAL IMPLEMENTED $90,010 $81,472 $55,631
1,158,979
kWh
$27,855
-
kW-mo/yr
$1,974
-
MMBtu
$4,550
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #1 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs