Assessment Year | 2015 |
---|---|
Principal Product | Corrugted and Solid Fiber Boxes |
NAICS | 322299: All Other Converted Paper Product Manufacturing |
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 110 |
Plant Area |
150,000
ft2
|
Annual Production | 590,000
thousand feet
|
Production Hrs. Annual | 7,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $388,989 | 5,987,507 |
kWh
|
$0.065 |
Electricity Demand | $104,351 | 12,689 |
kW-mo/yr
|
$8.22 |
Electricity Fees | $60,026 | - |
|
- |
Natural Gas | $196,075 | 33,679 |
MMBtu
|
$5.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,713 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,418 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,939 | $91,936 |
$21,358
328,583
kWh
|
$4,581
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,212 | $1,670 |
$14,870
228,771
kWh
|
$4,342
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $11,915 | $1,856 |
$11,915
183,315
kWh
|
- | - | - | - | |
04 | 2.4323: Use optimum size and capacity equipment | $9,840 | $4,691 |
$8,853
136,196
kWh
|
$987
-
kW-mo/yr
|
- | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $6,547 | $280 | - | - | - | - | $6,547 | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,388 | $40 |
$4,401
67,708
kWh
|
$987
-
kW-mo/yr
|
- | - | - | |
07 | 2.2515: Use optimum thickness insulation | $5,040 | $1,810 | - | - | - |
$5,040
-
MMBtu
|
- | |
08 | 2.3132: Recharge batteries on during off-peak demand periods | $4,441 | $3,140 | - |
$4,441
-
kW-mo/yr
|
- | - | - | |
09 | 2.7233: Use properly designed and sized hvac equipment | $3,903 | $5,740 |
$2,603
40,040
kWh
|
- | $1,300 | - | - | |
10 | 2.6218: Turn off equipment when not in use | $2,706 | $1,300 |
$2,228
34,723
kWh
|
$478
-
kW-mo/yr
|
- | - | - | |
11 | 2.7221: Lower temperature during the winter season and vice-versa | $2,333 | $80 |
$1,633
25,122
kWh
|
$700
-
kW-mo/yr
|
- | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,619 | $3,040 |
$1,619
24,898
kWh
|
- | - | - | - | |
13 | 2.7145: Install skylights | $830 | $2,100 |
$683
10,514
kWh
|
$147
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $99,713 | $117,683 |
$70,163
1,079,870
kWh
|
$16,663
-
kW-mo/yr
|
$1,300 |
$5,040
-
MMBtu
|
$6,547 | ||
TOTAL IMPLEMENTED | $65,418 | $99,717 |
$53,343
821,103
kWh
|
$12,075
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs