ITAC Assessment: MI0263
ITAC logo
ITAC Assessment: MI0263
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Fruit Juice
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 200,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 5,616
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $327,181 3,531,240
kWh
Electricity Demand $93,198 12,897
kW-mo/yr
Electricity Fees $24,189 -
Natural Gas $75,906 9,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,008 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,319

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.6218: Turn off equipment when not in use $23,147 $3,600 $19,852
213,460
kWh
$3,295
-
kW-mo/yr
- -
02 2.6218: Turn off equipment when not in use $11,051 $500 $9,830
105,700
kWh
$1,221
-
kW-mo/yr
- -
03 2.2414: Use waste heat from hot flue gases to preheat $13,762 $28,000 - - $13,762
-
MMBtu
-
04 2.2447: Heat water with exhaust heat $6,564 $8,859 - - $6,564
-
MMBtu
-
05 2.2614: Use cooling tower or economizer to replace chiller cooling $4,131 $4,980 $3,543
38,091
kWh
$588
-
kW-mo/yr
- -
06 3.4116: Meter recycled water (to reduce sewer charges) $3,052 $560 - - - $3,052
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,377 $10,770 $2,037
21,902
kWh
$340
-
kW-mo/yr
- -
08 2.7135: Install occupancy sensors $1,643 $497 $1,412
15,181
kWh
$231
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,472 $1,660 $1,305
14,032
kWh
$167
-
kW-mo/yr
- -
10 2.2515: Use optimum thickness insulation $1,375 $360 - - $1,375
-
MMBtu
-
11 2.4231: Reduce the pressure of compressed air to the minimum required $1,317 $80 $1,120
12,047
kWh
$197
-
kW-mo/yr
- -
12 2.2511: Insulate bare equipment $708 $280 $607
6,526
kWh
$101
-
kW-mo/yr
- -
13 2.7221: Lower temperature during the winter season and vice-versa $409 $173 $351
3,774
kWh
$58
-
kW-mo/yr
- -
TOTAL RECOMMENDED $71,008 $60,319 $40,057
430,713
kWh
$6,198
-
kW-mo/yr
$21,701
-
MMBtu
$3,052
TOTAL IMPLEMENTED $20,319 $3,830 $14,018
150,734
kWh
$1,874
-
kW-mo/yr
$1,375
-
MMBtu
$3,052
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs