Assessment Year | 2014 |
---|---|
Principal Product | Fruit Juice |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
200,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $327,181 | 3,531,240 |
kWh
|
$0.093 |
Electricity Demand | $93,198 | 12,897 |
kW-mo/yr
|
$7.23 |
Electricity Fees | $24,189 | - |
|
- |
Natural Gas | $75,906 | 9,035 |
MMBtu
|
$8.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,008 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,319 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $23,147 | $3,600 |
$19,852
213,460
kWh
|
$3,295
-
kW-mo/yr
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $11,051 | $500 |
$9,830
105,700
kWh
|
$1,221
-
kW-mo/yr
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $13,762 | $28,000 | - | - |
$13,762
-
MMBtu
|
- | |
04 | 2.2447: Heat water with exhaust heat | $6,564 | $8,859 | - | - |
$6,564
-
MMBtu
|
- | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $4,131 | $4,980 |
$3,543
38,091
kWh
|
$588
-
kW-mo/yr
|
- | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,052 | $560 | - | - | - | $3,052 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,377 | $10,770 |
$2,037
21,902
kWh
|
$340
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $1,643 | $497 |
$1,412
15,181
kWh
|
$231
-
kW-mo/yr
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,472 | $1,660 |
$1,305
14,032
kWh
|
$167
-
kW-mo/yr
|
- | - | |
10 | 2.2515: Use optimum thickness insulation | $1,375 | $360 | - | - |
$1,375
-
MMBtu
|
- | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,317 | $80 |
$1,120
12,047
kWh
|
$197
-
kW-mo/yr
|
- | - | |
12 | 2.2511: Insulate bare equipment | $708 | $280 |
$607
6,526
kWh
|
$101
-
kW-mo/yr
|
- | - | |
13 | 2.7221: Lower temperature during the winter season and vice-versa | $409 | $173 |
$351
3,774
kWh
|
$58
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $71,008 | $60,319 |
$40,057
430,713
kWh
|
$6,198
-
kW-mo/yr
|
$21,701
-
MMBtu
|
$3,052 | ||
TOTAL IMPLEMENTED | $20,319 | $3,830 |
$14,018
150,734
kWh
|
$1,874
-
kW-mo/yr
|
$1,375
-
MMBtu
|
$3,052 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs