| Assessment Year | 2012 |
|---|---|
| Principal Product | Light Truck and Utility Vehicle |
| NAICS | 336112: Light Truck and Utility Vehicle Manufacturing |
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
120,000
ft2
|
| Annual Production | 1,000
pieces
|
| Production Hrs. Annual | 2,496
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $146,728 | 1,726,986 |
kWh
|
$0.085 |
| Electricity Demand | $34,467 | 7,048 |
kW-mo/yr
|
$4.89 |
| Electricity Fees | $10,604 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,455 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $43,556 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4111: Use closed cycle process to minimize waste water production | $23,380 | $25,234 | - | - | $23,380 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,340 | $39,360 |
$12,016
141,373
kWh
|
$3,324
-
kW-mo/yr
|
- | |
| 03 | 2.7145: Install skylights | $7,706 | $13,800 |
$6,066
69,728
kWh
|
$1,640
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,310 | $1,660 |
$2,557
30,082
kWh
|
$3,753
-
kW-mo/yr
|
- | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $5,132 | $1,400 |
$3,303
38,858
kWh
|
$1,829
-
kW-mo/yr
|
- | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $4,409 | $80 |
$3,455
40,651
kWh
|
$954
-
kW-mo/yr
|
- | |
| 07 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $3,519 | $11,300 |
$2,267
26,672
kWh
|
$1,252
-
kW-mo/yr
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,579 | $1,660 |
$1,224
14,405
kWh
|
$355
-
kW-mo/yr
|
- | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,502 | $80 |
$1,195
14,053
kWh
|
$307
-
kW-mo/yr
|
- | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $922 | $80 |
$707
8,323
kWh
|
$215
-
kW-mo/yr
|
- | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $656 | $3,010 |
$514
6,055
kWh
|
$142
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $70,455 | $97,664 |
$33,304
390,200
kWh
|
$13,771
-
kW-mo/yr
|
$23,380 | ||
| TOTAL IMPLEMENTED | $43,556 | $61,130 |
$31,037
363,528
kWh
|
$12,519
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs