ITAC Assessment: MI0220
ITAC logo
ITAC Assessment: MI0220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Food Product Machinery
NAICS 333318: Other Commercial and Service Industry Machinery Manufacturing
SIC 3589: Service Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 300,000
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $216,594 2,478,116
kWh
Electricity Demand $68,502 8,155
kW-mo/yr
Electricity Fees $26,364 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,347 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $29,181 $52,934 $20,487
235,490
kWh
$8,694
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $13,778 $1,800 $12,165
139,828
kWh
$1,613
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,280 $1,660 $6,220
71,491
kWh
$2,060
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,676 $20,320 $4,685
53,848
kWh
$1,991
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $6,448 $80 $4,811
55,303
kWh
$1,637
-
kW-mo/yr
06 2.6218: Turn off equipment when not in use $5,329 $40 $3,741
42,998
kWh
$1,588
-
kW-mo/yr
07 2.7221: Lower temperature during the winter season and vice-versa $4,050 $200 $2,840
32,648
kWh
$1,210
-
kW-mo/yr
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,863 $5,850 $2,712
31,163
kWh
$1,151
-
kW-mo/yr
09 2.6218: Turn off equipment when not in use $2,772 $545 $1,949
22,408
kWh
$823
-
kW-mo/yr
10 2.7496: Install partitions to reduce size of conditioned space $2,072 $5,800 $1,455
16,721
kWh
$617
-
kW-mo/yr
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,014 $320 $712
8,185
kWh
$302
-
kW-mo/yr
12 2.7145: Install skylights $978 $1,920 $684
7,862
kWh
$294
-
kW-mo/yr
13 2.6218: Turn off equipment when not in use $906 $208 $637
7,319
kWh
$269
-
kW-mo/yr
TOTAL RECOMMENDED $85,347 $91,677 $63,098
725,264
kWh
$22,249
-
kW-mo/yr
TOTAL IMPLEMENTED $40,783 $6,228 $31,810
365,634
kWh
$8,973
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs