Assessment Year | 2011 |
---|---|
Principal Product | Fruit Juice |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 500 |
Plant Area |
360,220
ft2
|
Annual Production | 25,000
Tgal
|
Production Hrs. Annual | 4,284
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,741,806 | 37,391,841 |
kWh
|
$0.073 |
Electricity Demand | $498,673 | 71,239 |
kW-mo/yr
|
$7.00 |
Electricity Fees | $20,197 | - |
|
- |
Fuel Oil #2 | $3,486,258 | 160,673 |
MMBtu
|
$21.70 |
Fuel Oil #6 | $3,197,676 | 217,981 |
MMBtu
|
$14.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,220,446 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,746,720 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1332: Convert combustion equipment to burn natural gas | $4,297,734 | $3,000,000 | - | - |
$367,716
-
MMBtu
|
$323,077
-
MMBtu
|
$3,606,941 | |
02 | 2.2447: Heat water with exhaust heat | $240,185 | $30,000 | - | - |
$240,185
-
MMBtu
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $192,436 | $36,000 | - | - |
$192,436
-
MMBtu
|
- | - | |
04 | 3.4159: Replace treated water with well / surface water | $132,137 | $500,000 |
$61,907
884,389
kWh
|
$20,230
-
kW-mo/yr
|
- | - | $50,000 | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $112,996 | $1,950 | - | - |
$112,996
-
MMBtu
|
- | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $107,940 | $330,568 |
$87,395
1,197,175
kWh
|
$20,545
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,204 | $29,679 |
$28,249
403,553
kWh
|
$3,955
-
kW-mo/yr
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,599 | $1,320 |
$24,611
337,132
kWh
|
$2,988
-
kW-mo/yr
|
- | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,681 | $50 |
$11,892
162,907
kWh
|
$1,789
-
kW-mo/yr
|
- | - | - | |
10 | 2.7221: Lower temperature during the winter season and vice-versa | $22,382 | $2,550 |
$19,631
280,439
kWh
|
$2,751
-
kW-mo/yr
|
- | - | - | |
11 | 2.7425: Clean or color roof to reduce solar load | $10,779 | $45,345 |
$5,736
81,943
kWh
|
$5,043
-
kW-mo/yr
|
- | - | - | |
12 | 2.2136: Install / repair insulation on steam lines | $13,268 | $3,200 | - | - |
$13,268
-
MMBtu
|
- | - | |
13 | 4.514: Re-arrange equipment layout to reduce handling costs | $7,944 | $2,000 |
$6,971
99,590
kWh
|
$973
-
kW-mo/yr
|
- | - | - | |
14 | 2.6218: Turn off equipment when not in use | $5,235 | $3,450 |
$5,235
74,784
kWh
|
- | - | - | - | |
15 | 2.6218: Turn off equipment when not in use | $3,926 | $3,450 |
$3,926
56,088
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $5,220,446 | $3,989,562 |
$255,553
3,578,000
kWh
|
$58,274
-
kW-mo/yr
|
$926,601
-
MMBtu
|
$323,077
-
MMBtu
|
$3,656,941 | ||
TOTAL IMPLEMENTED | $4,746,720 | $3,873,667 |
$223,215
3,116,028
kWh
|
$49,507
-
kW-mo/yr
|
$493,980
-
MMBtu
|
$323,077
-
MMBtu
|
$3,656,941 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs