Assessment Year | 2009 |
---|---|
Principal Product | Paint |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
36,000
ft2
|
Annual Production | 15,000
Tgal
|
Production Hrs. Annual | 5,100
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $320,546 | 3,994,000 |
kWh
|
$0.080 |
Electricity Demand | $54,371 | 15,173 |
kW-mo/yr
|
$3.58 |
Electricity Fees | $31,547 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,016 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $98,598 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,441 | $12,707 |
$24,095
273,191
kWh
|
$2,346
-
kW-mo/yr
|
|
02 | 2.6218: Turn off equipment when not in use | $24,940 | $10,000 |
$22,698
257,347
kWh
|
$2,242
-
kW-mo/yr
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,913 | $40 |
$15,780
178,914
kWh
|
$3,133
-
kW-mo/yr
|
|
04 | 2.7221: Lower temperature during the winter season and vice-versa | $14,610 | $2,000 |
$13,800
156,468
kWh
|
$810
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,694 | $1,210 |
$12,091
137,086
kWh
|
$1,603
-
kW-mo/yr
|
|
06 | 2.7135: Install occupancy sensors | $7,828 | $13,850 |
$7,125
80,784
kWh
|
$703
-
kW-mo/yr
|
|
07 | 2.4322: Use or replace with energy efficient substitutes | $7,590 | $10,746 |
$6,832
77
kWh
|
$758
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $114,016 | $50,553 |
$102,421
1,083,867
kWh
|
$11,595
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $98,598 | $25,957 |
$88,464
1,003,006
kWh
|
$10,134
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs