ITAC Assessment: MI0182
ITAC logo
ITAC Assessment: MI0182
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Paint
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 36,000
ft2
Annual Production 15,000
Tgal
Production Hrs. Annual 5,100
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $320,546 3,994,000
kWh
Electricity Demand $54,371 15,173
kW-mo/yr
Electricity Fees $31,547 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,016 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $98,598

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $26,441 $12,707 $24,095
273,191
kWh
$2,346
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $24,940 $10,000 $22,698
257,347
kWh
$2,242
-
kW-mo/yr
03 2.4231: Reduce the pressure of compressed air to the minimum required $18,913 $40 $15,780
178,914
kWh
$3,133
-
kW-mo/yr
04 2.7221: Lower temperature during the winter season and vice-versa $14,610 $2,000 $13,800
156,468
kWh
$810
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,694 $1,210 $12,091
137,086
kWh
$1,603
-
kW-mo/yr
06 2.7135: Install occupancy sensors $7,828 $13,850 $7,125
80,784
kWh
$703
-
kW-mo/yr
07 2.4322: Use or replace with energy efficient substitutes $7,590 $10,746 $6,832
77
kWh
$758
-
kW-mo/yr
TOTAL RECOMMENDED $114,016 $50,553 $102,421
1,083,867
kWh
$11,595
-
kW-mo/yr
TOTAL IMPLEMENTED $98,598 $25,957 $88,464
1,003,006
kWh
$10,134
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs