ITAC Assessment: MI0166
ITAC logo
ITAC Assessment: MI0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Circuit Boards
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 150,000
ft2
Annual Production 46,500
units
Production Hrs. Annual 8,400
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,080,380 14,302,800
kWh
Electricity Demand $86,888 25,584
kW-mo/yr
Electricity Fees $170,902 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $484,438 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $122,668

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2628: Utilize a less expensive cooling method $360,093 $695,000 $341,451
3,910,832
kWh
$18,642
-
kW-mo/yr
02 2.7221: Lower temperature during the winter season and vice-versa $70,996 $1,200 $65,335
746,692
kWh
$5,661
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $30,899 $41,800 $28,435
324,972
kWh
$2,464
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $19,060 $1,210 $18,727
214,025
kWh
$333
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,713 $40 $1,568
17,917
kWh
$145
-
kW-mo/yr
06 2.4323: Use optimum size and capacity equipment $1,677 $3,475 $1,537
17,571
kWh
$140
-
kW-mo/yr
TOTAL RECOMMENDED $484,438 $742,725 $457,053
5,232,009
kWh
$27,385
-
kW-mo/yr
TOTAL IMPLEMENTED $122,668 $44,250 $114,065
1,303,606
kWh
$8,603
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs