| Assessment Year | 2008 |
|---|---|
| Principal Product | Circuit Boards |
| NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
150,000
ft2
|
| Annual Production | 46,500
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,080,380 | 14,302,800 |
kWh
|
$0.076 |
| Electricity Demand | $86,888 | 25,584 |
kW-mo/yr
|
$3.40 |
| Electricity Fees | $170,902 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $484,438 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $122,668 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2628: Utilize a less expensive cooling method | $360,093 | $695,000 |
$341,451
3,910,832
kWh
|
$18,642
-
kW-mo/yr
|
|
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $70,996 | $1,200 |
$65,335
746,692
kWh
|
$5,661
-
kW-mo/yr
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,899 | $41,800 |
$28,435
324,972
kWh
|
$2,464
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,060 | $1,210 |
$18,727
214,025
kWh
|
$333
-
kW-mo/yr
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,713 | $40 |
$1,568
17,917
kWh
|
$145
-
kW-mo/yr
|
|
| 06 | 2.4323: Use optimum size and capacity equipment | $1,677 | $3,475 |
$1,537
17,571
kWh
|
$140
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $484,438 | $742,725 |
$457,053
5,232,009
kWh
|
$27,385
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $122,668 | $44,250 |
$114,065
1,303,606
kWh
|
$8,603
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs