Assessment Year | 2008 |
---|---|
Principal Product | Circuit Boards |
NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
150,000
ft2
|
Annual Production | 46,500
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,080,380 | 14,302,800 |
kWh
|
$0.076 |
Electricity Demand | $86,888 | 25,584 |
kW-mo/yr
|
$3.40 |
Electricity Fees | $170,902 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $484,438 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $122,668 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $360,093 | $695,000 |
$341,451
3,910,832
kWh
|
$18,642
-
kW-mo/yr
|
|
02 | 2.7221: Lower temperature during the winter season and vice-versa | $70,996 | $1,200 |
$65,335
746,692
kWh
|
$5,661
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,899 | $41,800 |
$28,435
324,972
kWh
|
$2,464
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,060 | $1,210 |
$18,727
214,025
kWh
|
$333
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,713 | $40 |
$1,568
17,917
kWh
|
$145
-
kW-mo/yr
|
|
06 | 2.4323: Use optimum size and capacity equipment | $1,677 | $3,475 |
$1,537
17,571
kWh
|
$140
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $484,438 | $742,725 |
$457,053
5,232,009
kWh
|
$27,385
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $122,668 | $44,250 |
$114,065
1,303,606
kWh
|
$8,603
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs