| Assessment Year | 2007 |
|---|---|
| Principal Product | Dair Products |
| NAICS | 311511: Fluid Milk Manufacturing |
| SIC | 2026: Fluid Milk |
| Sales Range | $100 M to 500M |
| # of Employees | 260 |
| Plant Area |
250,000
ft2
|
| Annual Production | 105,270
Tgal
|
| Production Hrs. Annual | 7,280
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,487,636 | 36,700,000 |
kWh
|
$0.068 |
| Electricity Demand | $311,580 | 34,620 |
kW-mo/yr
|
$9.00 |
| Electricity Fees | $195,850 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $597,859 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $93,214 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2447: Heat water with exhaust heat | $406,657 | $46,000 | - | - |
$406,657
-
MMBtu
|
|
| 02 | 2.6218: Turn off equipment when not in use | $70,674 | $34 |
$59,797
882,220
kWh
|
$10,877
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $46,802 | $1,074 |
$37,580
726,930
kWh
|
$9,222
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,407 | $68,250 |
$30,791
454,272
kWh
|
$5,616
-
kW-mo/yr
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $22,540 | $850 |
$19,157
273,624
kWh
|
$3,383
-
kW-mo/yr
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $14,779 | $30 |
$11,691
172,486
kWh
|
$3,088
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $597,859 | $116,238 |
$159,016
2,509,532
kWh
|
$32,186
-
kW-mo/yr
|
$406,657
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $93,214 | $884 |
$78,954
1,155,844
kWh
|
$14,260
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs