ITAC Assessment: MI0142
ITAC logo
ITAC Assessment: MI0142
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Dair Products
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 260
Plant Area 250,000
ft2
Annual Production 105,270
Tgal
Production Hrs. Annual 7,280
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,487,636 36,700,000
kWh
Electricity Demand $311,580 34,620
kW-mo/yr
Electricity Fees $195,850 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $597,859 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $93,214

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2447: Heat water with exhaust heat $406,657 $46,000 - - $406,657
-
MMBtu
02 2.6218: Turn off equipment when not in use $70,674 $34 $59,797
882,220
kWh
$10,877
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $46,802 $1,074 $37,580
726,930
kWh
$9,222
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $36,407 $68,250 $30,791
454,272
kWh
$5,616
-
kW-mo/yr
-
05 2.6218: Turn off equipment when not in use $22,540 $850 $19,157
273,624
kWh
$3,383
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $14,779 $30 $11,691
172,486
kWh
$3,088
-
kW-mo/yr
-
TOTAL RECOMMENDED $597,859 $116,238 $159,016
2,509,532
kWh
$32,186
-
kW-mo/yr
$406,657
-
MMBtu
TOTAL IMPLEMENTED $93,214 $884 $78,954
1,155,844
kWh
$14,260
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs