Assessment Year | 2006 |
---|---|
Principal Product | Plastics |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 240 |
Plant Area |
60,000
ft2
|
Annual Production | 33,600,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $479,389 | 7,787,842 |
kWh
|
$0.062 |
Electricity Demand | $154,558 | 18,979 |
kW-mo/yr
|
$8.14 |
Electricity Fees | $75,970 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $131,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,043 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $86,700 | $3,400 |
$85,438
1,137,650
kWh
|
$1,262
-
kW-mo/yr
|
|
02 | 2.6218: Turn off equipment when not in use | $34,704 | - |
$34,200
454,260
kWh
|
$504
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,100 | $10,050 |
$3,456
46,085
kWh
|
$644
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,584 | $964 |
$2,099
27,953
kWh
|
$485
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,755 | $30 |
$1,450
19,304
kWh
|
$305
-
kW-mo/yr
|
|
06 | 2.4323: Use optimum size and capacity equipment | $1,350 | $3,400 |
$1,193
15,884
kWh
|
$157
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $131,193 | $17,844 |
$127,836
1,701,136
kWh
|
$3,357
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $39,043 | $994 |
$37,749
501,517
kWh
|
$1,294
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs