| Assessment Year | 2005 |
|---|---|
| Principal Product | Plastic Injection Molding |
| NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 40 |
| Plant Area |
15,000
ft2
|
| Annual Production | 60,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $90,371 | 1,569,767 |
kWh
|
$0.058 |
| Electricity Demand | $25,454 | 3,199 |
kW-mo/yr
|
$7.96 |
| Electricity Fees | $12,105 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,087 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,893 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $5,669 | - |
$4,539
81,996
kWh
|
$1,130
-
kW-mo/yr
|
|
| 02 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $3,836 | $122 |
$3,087
53,759
kWh
|
$749
-
kW-mo/yr
|
|
| 03 | 2.2511: Insulate bare equipment | $2,209 | $420 |
$1,769
31,963
kWh
|
$440
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,015 | $964 |
$1,658
29,941
kWh
|
$357
-
kW-mo/yr
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $996 | $56 |
$722
13,038
kWh
|
$274
-
kW-mo/yr
|
|
| 06 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $362 | - |
$292
5,076
kWh
|
$70
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $15,087 | $1,562 |
$12,067
215,773
kWh
|
$3,020
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $9,893 | $1,384 |
$7,966
143,900
kWh
|
$1,927
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs