Assessment Year | 2005 |
---|---|
Principal Product | Asphalt |
NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
100,000
ft2
|
Annual Production | 5,000,000
ton
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,905 | 1,149,600 |
kWh
|
$0.052 |
Electricity Demand | $49,215 | 5,935 |
kW-mo/yr
|
$8.29 |
Electricity Fees | $11,730 | - |
|
- |
Other Gas | $1,863,020 | 931,281 |
MMBtu
|
$2.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $332,807 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1116: Improve combustion control capability | $178,061 | $75,000 | - | - |
$178,061
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $145,490 | $5,540 | - | - |
$145,490
-
MMBtu
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,318 | - |
$2,721
2,721
kWh
|
$2,597
-
kW-mo/yr
|
- | |
04 | 2.4323: Use optimum size and capacity equipment | $1,956 | $5,024 |
$1,526
29,289
kWh
|
$430
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,982 | $56 |
$938
18,000
kWh
|
$1,044
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $332,807 | $85,620 |
$5,185
50,010
kWh
|
$4,071
-
kW-mo/yr
|
$323,551
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs