Assessment Year | 2004 |
---|---|
Principal Product | Industrial injection molded plastic products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
105,000
ft2
|
Annual Production | 520,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $503,368 | 10,670,400 |
kWh
|
$0.047 |
Electricity Demand | $173,010 | 21,208 |
kW-mo/yr
|
$8.16 |
Electricity Fees | $73,723 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,680 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $18,276 | $600 | - | - | $18,276 | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,092 | $3,064 |
$1,092
16,970
kWh
|
- | - | - | |
03 | 2.2511: Insulate bare equipment | $11,977 | $1,982 |
$1,993
55,776
kWh
|
- | - | $9,984 | |
04 | 4.131: Modify process to reduce material use/cost | $21,570 | $30,000 | - | - | - | $21,570 | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $2,291 | $360 |
$2,291
48,840
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,474 | $590 |
$4,554
91,760
kWh
|
$(-2,080.0) | - | - | |
TOTAL RECOMMENDED | $57,680 | $36,596 |
$9,930
213,346
kWh
|
$(-2,080.0) | $18,276 | $31,554 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs