Assessment Year | 2004 |
---|---|
Principal Product | Juice extraction, packaging and pellets |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 135 |
Plant Area |
254,800
ft2
|
Annual Production | 214,986
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $634,626 | 13,584,648 |
kWh
|
$0.047 |
Electricity Demand | $238,810 | 29,746 |
kW-mo/yr
|
$8.03 |
Electricity Fees | $11,992 | - |
|
- |
Fuel Oil #6 | $3,422,952 | 539,487 |
MMBtu
|
$6.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $370,405 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $138,625 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $21,521 | $600 | - | - | $21,521 | |
02 | 2.2136: Install / repair insulation on steam lines | $7,957 | $1,649 | - |
$7,957
-
MMBtu
|
- | |
03 | 2.1221: Replace obsolete burners with more efficient ones | $108,501 | $33,050 | - |
$108,501
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,693 | $250 |
$1,693
33,916
kWh
|
- | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $138,625 | $68,380 | - |
$138,625
-
MMBtu
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,937 | $61,795 |
$19,937
399,483
kWh
|
- | - | |
07 | 2.2511: Insulate bare equipment | $778 | $178 |
$778
15,594
kWh
|
- | - | |
08 | 2.2136: Install / repair insulation on steam lines | $3,053 | $450 | - |
$3,053
-
MMBtu
|
- | |
09 | 2.2135: Repair and eliminate steam leaks | $60,234 | $5,408 | - |
$60,234
-
MMBtu
|
- | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,416 | $2,670 |
$4,416
88,483
kWh
|
- | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,690 | - |
$3,690
73,790
kWh
|
- | - | |
TOTAL RECOMMENDED | $370,405 | $174,430 |
$30,514
611,266
kWh
|
$318,370
-
MMBtu
|
$21,521 | ||
TOTAL IMPLEMENTED | $138,625 | $68,380 | - |
$138,625
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs