Assessment Year | 2004 |
---|---|
Principal Product | Asphalt Mix |
NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
70,000
ft2
|
Annual Production | 273,000
ton
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $28,614 | 599,760 |
kWh
|
$0.048 |
Electricity Demand | $32,220 | 4,069 |
kW-mo/yr
|
$7.92 |
Electricity Fees | $8,110 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $172,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $566 | $600 | n/a | - | - | - | $566 | - |
02 | 2.6218: Turn off equipment when not in use | $396 | $175 | n/a |
$396
8,312
kWh
|
- | - | - | - |
03 | 2.2511: Insulate bare equipment | $5,493 | $942 | n/a |
$5,493
91,478
kWh
|
- | - | - | - |
04 | 2.4314: Use synthetic lubricant | $5,140 | $13,056 | n/a |
$1,612
29,988
kWh
|
- |
$408
-
gal
|
- | $3,120 |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $847 | $420 | n/a |
$847
18,745
kWh
|
- | - | - | - |
06 | 2.2424: Use heat in flue gases to preheat products or materials | $7,692 | $795 | n/a | - |
$7,692
-
MMBtu
|
- | - | - |
07 | 2.2514: Cover open tanks | $152,219 | $4,000 | n/a | - |
$218
-
MMBtu
|
- | - | $152,001 |
TOTAL RECOMMENDED | $172,353 | $19,988 |
$8,348
148,523
kWh
|
$7,910
-
MMBtu
|
$408
-
gal
|
$566 | $155,121 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs