Assessment Year | 2003 |
---|---|
Principal Product | Automotive Body Repair and Paint Shop |
NAICS | 811118: Other Automotive Mechanical and Electrical Repair and Maintenance |
SIC | 7539: Automotive Repair Shops, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
59,550
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,394 | 1,754,959 |
kWh
|
$0.057 |
Electricity Demand | $30,583 | 4,346 |
kW-mo/yr
|
$7.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,834 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $12,419 | - | n/a | - | $12,419 |
02 | 2.6218: Turn off equipment when not in use | $19,897 | $1,900 | n/a |
$19,897
455,686
kWh
|
- |
03 | 2.2136: Install / repair insulation on steam lines | $2,876 | $4,556 | n/a |
$2,876
63,661
kWh
|
- |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $207 | $325 | n/a |
$207
4,586
kWh
|
- |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $370 | $85 | n/a |
$370
8,205
kWh
|
- |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $42 | $231 | n/a |
$42
929
kWh
|
- |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $283 | $244 | n/a |
$283
6,256
kWh
|
- |
08 | 2.7232: Replace existing hvac unit with high efficiency model | $2,740 | $8,820 | n/a |
$2,740
60,642
kWh
|
- |
TOTAL RECOMMENDED | $38,834 | $16,161 |
$26,415
599,965
kWh
|
$12,419 | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs