ITAC Assessment: MI0057
ITAC logo
ITAC Assessment: MI0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Pharmaceutical (Tablets & Capsules)
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $50
M
to 100
M
# of Employees 264
Plant Area 46,723
ft2
Annual Production 375,000,000
pieces
Production Hrs. Annual 0
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $379,222 8,071,978
kWh
Electricity Demand $185,896 18,664
kW-mo/yr
Natural Gas $190,445 31,170
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $344,913 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,406

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $17,331 $1,000 - - - - $17,331
02 2.6218: Turn off equipment when not in use $10,356 $3,900 $10,356
147,943
kWh
- - - -
03 2.2113: Repair or replace steam traps $3,177 $1,160 - - $3,177
-
MMBtu
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,284 $441 $2,284
32,629
kWh
- - - -
05 2.4133: Use most efficient type of electric motors $2,707 $6,341 $2,285
32,275
kWh
$422
-
kW-mo/yr
- - -
06 2.7232: Replace existing hvac unit with high efficiency model $7,443 $400,000 $7,443
106,329
kWh
- - - -
07 2.2414: Use waste heat from hot flue gases to preheat $38,829 $70,000 - - $38,829
-
MMBtu
- -
08 3.4155: Meter waste water $12,786 $1,950 - - - $12,786
-
Tgal
-
09 3.6193: Install equipment (eg compactor) to reduce disposal costs $250,000 $43,000 - - - $250,000
-
Tgal
-
TOTAL RECOMMENDED $344,913 $527,792 $22,368
319,176
kWh
$422
-
kW-mo/yr
$42,006
-
MMBtu
$262,786
-
Tgal
$17,331
TOTAL IMPLEMENTED $23,406 $403,110 $7,443
106,329
kWh
- $3,177
-
MMBtu
$12,786
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs