ITAC Assessment: MI0048
ITAC logo
ITAC Assessment: MI0048
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Tablets and capsules
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $10
M
to 50
M
# of Employees 5
Plant Area 56,994
ft2
Annual Production 640,000,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $312,522 5,786,000
kWh
Electricity Demand $77,285 9,321
kW-mo/yr
Natural Gas $124,157 27,082
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,110,802 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,990,911

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Administrative Changes Savings Increase in Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $1,989,000 $115,000 - - - $1,989,000
02 4.111: Add equipment/ operators to reduce production bottleneck $1,989,000 $7,850 - - - $1,989,000
03 4.521: Clear and rent existing space $123,500 $300 - - $123,500 -
04 2.7232: Replace existing hvac unit with high efficiency model $6,814 $4,500 $6,814
61,152
kWh
- - -
05 2.7131: Add area lighting switches $1,911 $350 $1,911
70,762
kWh
- - -
06 3.4155: Meter waste water $577 $1,454 - $577
-
Tgal
- -
TOTAL RECOMMENDED $4,110,802 $129,454 $8,725
131,914
kWh
$577
-
Tgal
$123,500 $3,978,000
TOTAL IMPLEMENTED $1,990,911 $115,350 $1,911
70,762
kWh
- - $1,989,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs