ITAC Assessment: MI0044
ITAC logo
ITAC Assessment: MI0044
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Conduit and concrete pipes
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 15
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,680
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $110,802 1,878,000
kWh
Electricity Demand $45,448 5,724
kW-mo/yr
Natural Gas $66,233 13,517
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $240,703 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 4.323: Optimize lot sizes to reduce inventory carrying costs $180,000 $60 - - $180,000
02 4.431: Train operators for maximum operating efficiency $39,270 $28,000 - - $39,270
03 4.651: Install back-up equipment $12,320 $2,534 - - $12,320
04 2.7111: Reduce illumination to minimum necessary levels $2,885 $750 $2,885
49,720
kWh
- -
05 3.1161: Eliminate/reduce an operation $2,410 $48 $2,410
38,035
kWh
- -
06 2.4133: Use most efficient type of electric motors $2,072 $6,848 $1,538
25,634
kWh
$534
-
kW-mo/yr
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,746 $1 $1,746
29,094
kWh
- -
TOTAL RECOMMENDED $240,703 $38,241 $8,579
142,483
kWh
$534
-
kW-mo/yr
$231,590
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs