| Assessment Year | 2002 |
|---|---|
| Principal Product | Conduit and concrete pipes |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 15 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $110,802 | 1,878,000 |
kWh
|
$0.059 |
| Electricity Demand | $45,448 | 5,724 |
kW-mo/yr
|
$7.94 |
| Natural Gas | $66,233 | 13,517 |
MMBtu
|
$4.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $240,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.323: Optimize lot sizes to reduce inventory carrying costs | $180,000 | $60 | - | - | $180,000 | |
| 02 | 4.431: Train operators for maximum operating efficiency | $39,270 | $28,000 | - | - | $39,270 | |
| 03 | 4.651: Install back-up equipment | $12,320 | $2,534 | - | - | $12,320 | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $2,885 | $750 |
$2,885
49,720
kWh
|
- | - | |
| 05 | 3.1161: Eliminate/reduce an operation | $2,410 | $48 |
$2,410
38,035
kWh
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $2,072 | $6,848 |
$1,538
25,634
kWh
|
$534
-
kW-mo/yr
|
- | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,746 | $1 |
$1,746
29,094
kWh
|
- | - | |
| TOTAL RECOMMENDED | $240,703 | $38,241 |
$8,579
142,483
kWh
|
$534
-
kW-mo/yr
|
$231,590 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs