Assessment Year | 2002 |
---|---|
Principal Product | Conduit and concrete pipes |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 15 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,802 | 1,878,000 |
kWh
|
$0.059 |
Electricity Demand | $45,448 | 5,724 |
kW-mo/yr
|
$7.94 |
Natural Gas | $66,233 | 13,517 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $240,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 4.323: Optimize lot sizes to reduce inventory carrying costs | $180,000 | $60 | - | - | $180,000 | |
02 | 4.431: Train operators for maximum operating efficiency | $39,270 | $28,000 | - | - | $39,270 | |
03 | 4.651: Install back-up equipment | $12,320 | $2,534 | - | - | $12,320 | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $2,885 | $750 |
$2,885
49,720
kWh
|
- | - | |
05 | 3.1161: Eliminate/reduce an operation | $2,410 | $48 |
$2,410
38,035
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $2,072 | $6,848 |
$1,538
25,634
kWh
|
$534
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,746 | $1 |
$1,746
29,094
kWh
|
- | - | |
TOTAL RECOMMENDED | $240,703 | $38,241 |
$8,579
142,483
kWh
|
$534
-
kW-mo/yr
|
$231,590 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs