Assessment Year | 2002 |
---|---|
Principal Product | Cement production |
NAICS |
n/a
|
SIC | 1442: Construction Sand and Gravel |
Sales Range | $100 M to 500M |
# of Employees | 60 |
Plant Area |
55
ft2
|
Annual Production | 900,000
bbl
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $7,622,565 | 171,408,932 |
kWh
|
$0.044 |
Electricity Demand | $960,454 | 309,824 |
kW-mo/yr
|
$3.10 |
Natural Gas | $738,937 | 493,086 |
MMBtu
|
$1.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $742,678 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $26,947 | $1,040 |
$26,947
605,543
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $415,200 | $783,200 |
$415,200
9,330,337
kWh
|
- | |
03 | 2.4112: Install soft-start to eliminate nuisance trips | $46,426 | $44,225 | - |
$46,426
-
kW-mo/yr
|
|
04 | 2.4133: Use most efficient type of electric motors | $207,600 | $391,350 |
$207,600
4,613,333
kWh
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $46,505 | $41,115 |
$46,505
1,033,444
kWh
|
- | |
TOTAL RECOMMENDED | $742,678 | $1,260,930 |
$696,252
15,582,657
kWh
|
$46,426
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs