ITAC Assessment: MI0041
ITAC logo
ITAC Assessment: MI0041
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Cement production
NAICS
n/a
SIC 1442: Construction Sand and Gravel
Sales Range $100
M
to 500
M
# of Employees 60
Plant Area 55
ft2
Annual Production 900,000
bbl
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,622,565 171,408,932
kWh
Electricity Demand $960,454 309,824
kW-mo/yr
Natural Gas $738,937 493,086
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $742,678 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $26,947 $1,040 $26,947
605,543
kWh
-
02 2.4133: Use most efficient type of electric motors $415,200 $783,200 $415,200
9,330,337
kWh
-
03 2.4112: Install soft-start to eliminate nuisance trips $46,426 $44,225 - $46,426
-
kW-mo/yr
04 2.4133: Use most efficient type of electric motors $207,600 $391,350 $207,600
4,613,333
kWh
-
05 2.4133: Use most efficient type of electric motors $46,505 $41,115 $46,505
1,033,444
kWh
-
TOTAL RECOMMENDED $742,678 $1,260,930 $696,252
15,582,657
kWh
$46,426
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs