| Assessment Year | 2002 |
|---|---|
| Principal Product | Cement production |
| NAICS |
n/a
|
| SIC | 1442: Construction Sand and Gravel |
| Sales Range | $100 M to 500M |
| # of Employees | 60 |
| Plant Area |
55
ft2
|
| Annual Production | 900,000
bbl
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $7,622,565 | 171,408,932 |
kWh
|
$0.044 |
| Electricity Demand | $960,454 | 309,824 |
kW-mo/yr
|
$3.10 |
| Natural Gas | $738,937 | 493,086 |
MMBtu
|
$1.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $742,678 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $26,947 | $1,040 |
$26,947
605,543
kWh
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $415,200 | $783,200 |
$415,200
9,330,337
kWh
|
- | |
| 03 | 2.4112: Install soft-start to eliminate nuisance trips | $46,426 | $44,225 | - |
$46,426
-
kW-mo/yr
|
|
| 04 | 2.4133: Use most efficient type of electric motors | $207,600 | $391,350 |
$207,600
4,613,333
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $46,505 | $41,115 |
$46,505
1,033,444
kWh
|
- | |
| TOTAL RECOMMENDED | $742,678 | $1,260,930 |
$696,252
15,582,657
kWh
|
$46,426
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs