Assessment Year | 2002 |
---|---|
Principal Product | Cement and Concrete Aggregate |
NAICS |
n/a
|
SIC | 1442: Construction Sand and Gravel |
Sales Range | $100 M to 500M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 900,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $538,181 | 10,805,700 |
kWh
|
$0.050 |
Electricity Demand | $180,515 | 64,701 |
kW-mo/yr
|
$2.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $181,033 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $128,247 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Electricity Fees Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 4.651: Install back-up equipment | $16,380 | $17,500 | - | - | $16,380 | |
02 | 4.611: Begin a practice of predictive / preventative maintenance | $86,400 | $6,084 | - | - | $86,400 | |
03 | 3.1191: Change procedures / equipment / operating conditions | $25,467 | $18,252 | - | - | $25,467 | |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,252 | $30 | - | $2,252 | - | |
05 | 2.4112: Install soft-start to eliminate nuisance trips | $50,534 | $52,260 |
$50,534
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $181,033 | $94,126 |
$50,534
-
kW-mo/yr
|
$2,252 | $128,247 | ||
TOTAL IMPLEMENTED | $128,247 | $41,836 | - | - | $128,247 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs