Assessment Year | 2002 |
---|---|
Principal Product | multi-pin cicular and rectangular connectors |
NAICS |
n/a
|
SIC | 3678: Electronic Connectors |
Sales Range | $5 M to 10M |
# of Employees | 53 |
Plant Area |
18,600
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,319 | 459,900 |
kWh
|
$0.059 |
Electricity Demand | $9,034 | 1,234 |
kW-mo/yr
|
$7.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $214,553 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,613 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.112: Replace old machine with new automatic multi-station tool | $190,000 | $100,000 | - | - | - | $190,000 | |
02 | 4.111: Add equipment/ operators to reduce production bottleneck | $18,650 | $26,450 | - | - | $18,650 | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $3,094 | $4,500 |
$3,094
48,951
kWh
|
- | - | - | |
04 | 2.4112: Install soft-start to eliminate nuisance trips | $1,846 | $2,345 | - |
$1,846
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $963 | $250 | - | - | $963 | - | |
TOTAL RECOMMENDED | $214,553 | $133,545 |
$3,094
48,951
kWh
|
$1,846
-
kW-mo/yr
|
$19,613 | $190,000 | ||
TOTAL IMPLEMENTED | $19,613 | $26,700 | - | - | $19,613 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs