ITAC Assessment: MI0034
ITAC logo
ITAC Assessment: MI0034
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Building Supplies
NAICS
n/a
SIC 2431: Millwork
Sales Range $50
M
to 100
M
# of Employees 80
Plant Area 35,000
ft2
Annual Production 36,000
ton
Production Hrs. Annual 3,770
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,850 1,262,261
kWh
Electricity Demand $26,820 3,303
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $268,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Product Savings
01 4.521: Clear and rent existing space $114,920 $10,000 - - $65,520 $49,400
02 4.521: Clear and rent existing space $38,760 $120 - - $38,760 -
03 4.125: $49,218 $64 - - - $49,218
04 2.1321: Replace fossil fuel equipment with electrical equipment $31,945 $4,500 $(-2,933.0)
(-43,130)
kWh
$(-1,122.0)
-
kW-mo/yr
$36,000 -
05 4.521: Clear and rent existing space $23,880 $120 - - $16,380 $7,500
06 2.7232: Replace existing hvac unit with high efficiency model $7,201 $6,000 $7,201
80,964
kWh
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,913 $113 $2,913
42,337
kWh
- - -
TOTAL RECOMMENDED $268,837 $20,917 $7,181
80,171
kWh
$(-1,122.0)
-
kW-mo/yr
$156,660 $106,118
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs