| Assessment Year | 2002 |
|---|---|
| Principal Product | Crushed limestone,gravel,sand |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $50 M to 100M |
| # of Employees | 135 |
| Plant Area |
40,000
ft2
|
| Annual Production | 12,000,000
ton
|
| Production Hrs. Annual | 4,836
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $523,006 | 38,881,698 |
kWh
|
$0.013 |
| Electricity Demand | $1,951,227 | 188,592 |
kW-mo/yr
|
$10.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $366,146 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $72,800 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4112: Install soft-start to eliminate nuisance trips | $132,680 | $46,380 | - |
$132,680
-
kW-mo/yr
|
- | |
| 02 | 4.651: Install back-up equipment | $72,800 | $35,000 | - | - | $72,800 | |
| 03 | 4.611: Begin a practice of predictive / preventative maintenance | $60,800 | $5,460 | - | - | $60,800 | |
| 04 | 4.126: Install sensors to detect defects | $60,800 | $925 | - | - | $60,800 | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $39,066 | $2,938 |
$34,826
696,510
kWh
|
$4,240
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $366,146 | $90,703 |
$34,826
696,510
kWh
|
$136,920
-
kW-mo/yr
|
$194,400 | ||
| TOTAL IMPLEMENTED | $72,800 | $35,000 | - | - | $72,800 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs