ITAC Assessment: MI0013
ITAC logo
ITAC Assessment: MI0013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Marine exhaust systems
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 23,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 2,168
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,204 429,709
kWh
Electricity Demand $11,970 1,386
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $139,863 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings Primary Product Savings
01 4.513: Re-arrange equipment layout to reduce labor costs $1,255 $710 - - $1,255
02 4.111: Add equipment/ operators to reduce production bottleneck $114,000 $32,515 - - $114,000
03 3.3128: Utilize other methods to remove contaminants $3,000 $5,000 - - $3,000
04 4.522: Modify storage space to avoid rental of a warehouse $6,641 $1,050 - $3,253 $3,388
05 2.7144: Install spectral reflectors / delamp $3,176 $4,500 $3,176
20,950
kWh
- -
06 4.111: Add equipment/ operators to reduce production bottleneck $9,000 $680 - - $9,000
07 2.7221: Lower temperature during the winter season and vice-versa $2,791 $15 $2,791
19,337
kWh
- -
TOTAL RECOMMENDED $139,863 $44,470 $5,967
40,287
kWh
$3,253 $130,643
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs