ITAC Assessment: MI0012
ITAC logo
ITAC Assessment: MI0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Elevator cars and entrances
NAICS
n/a
SIC 3534: Elevators and Moving Stairways
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 70,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,470
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,709 581,820
kWh
Electricity Demand $26,950 3,180
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,399 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $74,399

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $656 $260 $656
12,370
kWh
- -
02 4.712: Utilize job costing software $58,500 $12,000 - - $58,500
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,550 $306 $3,550
71,000
kWh
- -
04 4.512: Condense operation into one building $5,315 $2,040 - - $5,315
05 2.7144: Install spectral reflectors / delamp $4,188 $5,000 $4,188
46,493
kWh
- -
06 2.3132: Recharge batteries on during off-peak demand periods $2,190 $29 - $2,190
-
kW-mo/yr
-
TOTAL RECOMMENDED $74,399 $19,635 $8,394
129,863
kWh
$2,190
-
kW-mo/yr
$63,815
TOTAL IMPLEMENTED $74,399 $19,635 $8,394
129,863
kWh
$2,190
-
kW-mo/yr
$63,815
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs