ITAC Assessment: MI0007
ITAC logo
ITAC Assessment: MI0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Metal fabrication/powder coating
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 115
Plant Area 90,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,550
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,942 1,368,705
kWh
Electricity Demand $31,632 3,790
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $211,929 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $147,929

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,671 $281 $8,671
109,516
kWh
-
02 4.122: Develop standard procedures to improve internal yields $138,240 $32,000 - $138,240
03 4.514: Re-arrange equipment layout to reduce handling costs $44,000 $5,841 - $44,000
04 2.7221: Lower temperature during the winter season and vice-versa $1,018 $11 $1,018
12,725
kWh
-
05 4.424: Improve space comfort conditioning $20,000 $5,000 - $20,000
TOTAL RECOMMENDED $211,929 $43,133 $9,689
122,241
kWh
$202,240
TOTAL IMPLEMENTED $147,929 $32,292 $9,689
122,241
kWh
$138,240
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs