ITAC Assessment: ME0297
ITAC logo
ITAC Assessment: ME0297
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Log Homes
NAICS
n/a
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $5
M
to 10
M
# of Employees 130
Plant Area
n/a
Annual Production 200
pieces
Production Hrs. Annual 4,225
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,363 1,450,176
kWh
Electricity Fees $1,601 -
Fuel Oil #1 $13,381 1,437
MMBtu
Fuel Oil #2 $26,425 3,720
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $368,996 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #1 Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings By-product Production Savings Increase in Production Savings
01 2.1331: Burn a less expensive grade of fuel $10,802 $30,000 n/a - $11,037
-
MMBtu
$(-235.0)
-
lb
- - - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,161 $8,745 n/a $3,161
29,308
kWh
- - - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,934 $8,265 n/a $2,934
26,084
kWh
- - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $964 $300 n/a $964
9,086
kWh
- - - - - -
05 3.1182: Make a new by-product $267,435 $280,836 n/a - - $(-6,064.0)
-
lb
$(-10,000.0) $(-11,813.0) $295,312 -
06 4.513: Re-arrange equipment layout to reduce labor costs $54,200 $28,115 n/a - - - $54,200 - - -
07 4.513: Re-arrange equipment layout to reduce labor costs $27,000 $14,835 n/a - - - - - - $27,000
08 4.513: Re-arrange equipment layout to reduce labor costs $2,500 $2,000 n/a - - - $2,500 - - -
TOTAL RECOMMENDED $368,996 $373,096 $7,059
64,478
kWh
$11,037
-
MMBtu
$(-6,299.0)
-
lb
$46,700 $(-11,813.0) $295,312 $27,000
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #1 Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings By-product Production Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs