Assessment Year | 2000 |
---|---|
Principal Product | Shoe Trees |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
100,000
ft2
|
Annual Production | 1,680,000
pieces
|
Production Hrs. Annual | 2,375
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $247,063 | 2,543,083 |
kWh
|
$0.097 |
Electricity Demand | $67,306 | 8,856 |
kW-mo/yr
|
$7.60 |
LPG | $10,075 | 1,426 |
MMBtu
|
$7.07 |
Wood | $7,488 | 8,640 |
MMBtu
|
$0.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,961 | $72,500 |
$18,332
189,039
kWh
|
$6,629
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,533 | $20,900 |
$10,533
108,734
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,918 | $11,100 |
$3,858
39,859
kWh
|
$1,060
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,043 | $860 |
$4,043
41,618
kWh
|
- | - | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $2,424 | $210 |
$2,424
24,912
kWh
|
- | - | - | - | - | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,656 | $1,330 |
$1,200
12,309
kWh
|
$456
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $815 | $1,600 |
$359
3,810
kWh
|
$456
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $112 | $130 |
$112
1,172
kWh
|
- | - | - | - | - | |
09 | 3.1182: Make a new by-product | $15,041 | $21,330 |
$(-21.0)
(-293)
kWh
|
- | $(-5,760.0) | $(-1,728.0) | $22,550 | - | |
10 | 4.122: Develop standard procedures to improve internal yields | $27,000 | $1,512 | - | - | - | - | - | $27,000 | |
TOTAL RECOMMENDED | $91,503 | $131,472 |
$40,840
421,160
kWh
|
$8,601
-
kW-mo/yr
|
$(-5,760.0) | $(-1,728.0) | $22,550 | $27,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs